Securing an Occupancy Permit
Submit Requirements: After clearances have been secured from the BFP, submit the duly accomplished forms and related documents, safety certificates, as-built plans (for any deviations from the approved plans) and detailed sketch of location.Afterwards, request for an inspection schedule
Staff evaluates documents and technical staff schedules for inspection
None
10 minutes
RYAN NOVIA, Laborer
MYLA LEDESMA, CE Engineer I
ADONIS JOSE GABRIEL, Arch II
Building Inspection
Building inspectors/technical staff conduct actual inspection of the completed building/structure
None
2 hours
MARY JEAN C. MAJADUCON, CE City Engineer
YVES MARI PATRIARCA, CE Engineer II
ROLLY DE LOS REYES, EE/ Engineer III
MYLA LEDESMA, CE Engineer III
FREEDIE PORRAS, ME Engineer I
Approval of Permits and Release of Certificate of Occupancy
Claim the approved Occupancy Permit and sign in the logbook
Building Official approves the Occupancy Permit.
Staff releases/issues Certificate of Occupancy
None
35 minutes
MARY JEAN C. MAJADUCON, CE City Engineer
RYAN NOVIA Laborer I
MYLA LEDESMA, CE Engineer III
Total:
Total assessment of schedule of fees based on the National Building Code
2 hours, 45 minutes
Contact
Osmeña Avenue, Victorias City, Negros Occidental 6119